The Russian Ministry of Industry and Trade has demanded that the Zelenograd Nanotechnology Center (ZNTC) pay 138.97 ₽ million in penalties. The fine relates to delays in the third stage of developing a domestic 130 nm lithography system.

The contract, signed on December 2, 2021, is valued at 5.55 ₽ billion with a final deadline of December 31, 2026. The third phase, which was due by March 31, 2026, was completed on August 7, 2026, after the company submitted the readiness notice in July.

ZNTC CEO Anatoly Kovalev attributed the delay to international sanctions imposed by the European Union on the company. Despite the setback, the company reports that it has already produced two 193 nm excimer laser prototypes and established key technological processes.

In October 2026, the parties amended the contract to include an 80% advance payment structure. Under the new terms, ZNTC is required to return 124 ₽ million in excess advance payments for the fourth stage and has adjusted penalty calculations for future non-compliance.

The project involves setting up an excimer laser at the NM-Tech facility in Zelenograd, while the stepper assembly is located at the ZNTC site. The company maintains that the overall project remains on schedule, with serial production planned for 2027.