Bitdeer Technologies Group, a Singapore-based company listed on Nasdaq under BTDR, has outlined a timeline for its AI cloud and high-performance computing expansion. The firm plans to initiate the 901 capacity delivery in January 2027, aiming to reach 67 MW by the second quarter of 2027.

The company's strategy centers on a campus in Johor Bahru, Malaysia. The A201 data center, featuring 21.7 MW of capacity, is scheduled to energize in Q1 2027. Bitdeer has secured commitments for over 70% of this site, projecting revenue exceeding $1.7 billion over five years.

The A202 site will add 65.1 MW of capacity with a target energization date in Q3 2027 under a 10-year agreement. Combined with the 9.5 MW A102 site, which is fully contracted and expected to generate over $800 million, the campus is set to reach 86.8 MW.

Bitdeer reports an expected revenue backlog for its AI Cloud business of approximately $2.9 billion. The company aims to deliver 350 MW of capacity by Q1 2028, having already secured about 333.5 MW through customer prepayments and contractual financing.

As a preferred NVIDIA Cloud Partner, Bitdeer maintains a vertically integrated model, allowing for flexible electricity allocation between Bitcoin mining and AI services. The company continues to advance GPU procurement and site agreements to support its infrastructure growth.