Norway’s grid operator, Statnett, has officially suspended new reservations for data center power capacity. This moratorium will remain in effect until at least August 2027.
The decision follows a surge in demand for power capacity from data centers. Total requests reached 31.3 GW, which exceeds the country’s current peak demand of slightly more than 25 GW.
Existing connections and projects that secured reservations prior to this decision are not affected by the new restrictions. Future initiatives will now face stricter requirements.
Market observers are monitoring whether this approach will influence grid management in Texas. Agencies such as ERCOT and the Texas Commission on Environmental Quality may consider similar measures.