Construction of the Marfino data center has reached several milestones over the summer. The energy center now features six completed foundations designed for three gas piston units and three diesel generator sets. Gas supply infrastructure has moved into the construction phase, with the main pipeline already installed.
Electrical work for the sewage pumping station is complete, with the equipment connected to the power grid and ready for testing. Commissioning of the station, including motor and automation cabinet checks, is scheduled for completion by the end of September.
The project documentation for the main data center building has been submitted to an expert organization for review. Additionally, the underground fiber-optic line has been fully installed, spliced, and tested, making the channel ready for operation.
Preparatory work for the first data center building is finished, including water analysis from the onsite well and the signing of a licensing agreement. Logistics for heavy equipment delivery have been finalized, with access routes secured for oversized transport.